GO Bond Funding: $1.99 million New I-45 Frontage Road to Hobbs Road Project Sheet (PDF)
Scope of work: Construct a new roadway from I-45 frontage road to Hobbs Road just south of the Cracker Barrel restaurant.


Project Status as of June 2021
GO Bond Project; programmed in CIP to begin design in FY2022 due to debt capacity.
Original Schedule
The original schedule, as of September 2019, has the design phase of the New I-45 Frontage Road to Hobbs project to begin in quarter 4 of 2021 through quarter 2 of 2023. Land acquisition is scheduled to begin quarter 3 of 2022 through quarter 2 of 2023. Construction bidding is scheduled for quarter 3 of 2023 with construction following beginning in quarter 4 of 2023 for a year. Construction time is an estimate as each bid is awarded based on cost and time submitted by the contractor.
Current Schedule
The current schedule, as of June 2021, shows the design phase of the new I-45 Frontage Road to Hobbs project beginning in quarter 4 of 2021 and lasting through quarter 2 of 2023. Land acquisition is scheduled to begin in quarter 3 of 2022 through quarter 2 of 2023. Construction bidding is scheduled for quarter 3 of 2023 with construction beginning in quarter 4 of 2023 for a year. Construction time is an estimate as each bid is awarded based on cost and time submitted by the contractor.