The Landing Subdivision Drainage Improvements

Budget: $475,000

Scope of work: Increase capacity and efficiency of existing drainage easements to enhance flow. Improve easements/rights-of-way with either earthen swales or concrete channels for unrestricted flow paths to Landing Ditch.

Subdivisions, areas, or streets impacted: The Landing

map

Landing drainage project timeline

Project Status as of May 2022

The consultant delivered 60% design plans in December 2021, which were reviewed by City staff and returned to the consultant with review comments. In late 2021, the Texas Historical Commission (THC) asked for additional documentation for this project. It was concluded in January 2022, that no historic properties are present or affected by the projects as proposed. The consultant delivered 90% design plans in April 2022, which were reviewed by City staff, and comments were returned to the consultant.  The consultant expects to deliver 100% design plans in June 2022. Construction phase to be determined; project is pending FEMA construction funding approval.

Original Schedule

The original schedule, as of September 2019, shows the preliminary study phase underway in 2019 with completion in quarter 4 of 2019 for The Landing Drainage Improvements. Design and land acquisition phases begins in quarter 1 of 2020 through quarter 3 of 2020. Construction bidding is scheduled for quarter 4 of 2020 with construction following through quarter 2 of 2022. Construction time is an estimate as each bid is awarded based on cost and time submitted by the contractor.

Current Schedule

The current schedule, as of December 2021, shows the completion of a grant application in quarter 3 of 2020 for The Landing Drainage Improvements. Grant award and kickoff were quarter 4 of 2020 through quarter 1 of 2021. RFQ for design services per the grant requirements completed in quarter 2 of 2021. Design begins in quarter 2 of 2021 and continues through quarter 3 of 2022. Land acquisition begins in quarter 1 in 2022 through quarter 2 of 2022. Construction bidding is scheduled for quarter 3 of 2022 with construction following in quarter 4 of 2022 through quarter 4 of 2023. Construction time is an estimate as each bid is awarded based on cost and time submitted by the contractor.