Dove Meadows Detention Pond

Budget: $5.3 million

Scope of work: Purchase land and construct a 115 acre-foot detention pond east of Blue Wing Drive and west of Borden’s Gully.

Subdivisions, areas, or streets impacted: Dove Meadows

map

project timeline-dove meadows-01

Project Status as of May 2022

The Nationwide Permit Verification was received from the United States Army Corp of Engineers (USACE) on April 16, 2021. The consultant delivered 90% design plans in April 2022, which were reviewed by City staff and review comments were returned to the consultant. A hearing for the land acquisition was held on April 2022, and the property was acquired for the location of the detention basin. The Mitigation Agreement to mitigate .47 acres of wetlands, which is a requirement as part of the USACE NWP was presented and approved by City Council in May 2022. The consultant delivered 100% design plans in May 2022, which are currently under review by City staff. City staff expects to bid the project for construction in the Summer of 2022.

Original Schedule

As of September 2019, shows design in progress in quarter 2 of 2019 through quarter 3 of 2020 for Dove Meadows & Borden's Gully Detention Pond. Land acquisition is programmed from quarter 1 through quarter 3 of 2020. Construction bidding is scheduled for quarter 4 of 2020 with construction following through quarter 1 of 2021. Construction time is an estimate as each bid is awarded based on cost and time submitted by the contractor.

Current Schedule

As of March 2021, for the Dove Meadows & Borden's Gully Detention Pond project shows design complete from quarter 2 of 2019 thru quarter 1 of 2021. Final design is programmed for quarter 4 of 2021. Land acquisition is shown in progress from quarter 1 of 2020 through quarter 3 of 2021. Permitting is shown in progress from quarter 4 of 2020 through quarter 3 of 2021. Construction bidding is in programmed for quarters 1 & 2 of 2022. Construction is programmed for quarter 3 of 2022 through quarter 4 of 2023. Construction time is an estimate as each bid is awarded based on cost and time submitted by the contractor.

Project Managers Contact Information